 1 Construction of Lying-In Clinic & RHU Bldg. Phase IV Brgy. East Poblacion, City of Naga  First Grandeur Builders  9,750,000 June 19, 2015 240 CD 90 CD May 13, 2016 100% Completed 5/12/16
2 Perimeter Fence Brgy. Tuyan, City of Naga Hoppers Builders 1,350,000 November 23, 2015 110 CD 28 CD April 8, 2016 100 % Completed 4/4/16
3 Perimeteer Fence (Phase 1) Brgy. Patag, City of Naga A.T. Macrohon Company Co. 1,350,000 November 23, 2015 90 CD N/A February 20, 2016 100% Completed 2/20/16
4 Construction of Drainage Sitio Tambis, Brgy. Inoburan, City of Naga  A.T. Macrohon Construction Co.  1,000,000 October 7, 2015 90 CD N/A January 5, 2016 100%

Completed 1/5/16

5 Construction of Grouted Riprap and Road Concreting Brgy. Alpaco, City of Naga A.T. Macrohon Construction Co. 2,210,000 January 15, 2016 120 CD N/A May 13, 2016 100 % Completed 4/25/16
6 Construction of Plant Nursery Brgy. Inoburan, City of Naga A.T. Macrohon Construction Co. 50,000 January 20, 2016 10 CD N/A January 27, 2016 100% Complete (canvass)
7 Rehab. of Drainage Brgy. South Poblacion, City of Naga A.T. Macrohon Co. 1,250,000 November 23,2015 45 CD N/A January 6, 2016 100%

Completed 1/5/16

8 Multi-purpose Bldg. (phase 2) Brgy. North Poblacion, City of Naga A.T. Macrohon Construction Co. 1,350,000 September 16, 2016 125 CD N/A January 18, 2016 100% Completed
9 Road Concreting Sitio Tal-ot, Mainit City of Naga A.T. Macrohon Construction Co. 1,215,000 November 23, 2016 50 CD N/A January 11, 2016 100% Completed 1/11/16
10 Covered Court Brgy. Lutac, City of Naga A.T. Macrohon Construction Co. 3,349,750.45 December 14, 2015 120 CD N/A April 12, 2016 80% On-going
11 Training Center w/ Food Court Brgy. East Poblacion, City of Naga Quirante Co. 8,000,000 December 14, 2015 90 CD N/A June 11, 2016 75% On-going
12 Rehabilitation of Drainage, Road Concreting & Const. Foot Bridge Brgy. Central Pob. City of Naga A.T. Macrohon Construction Co. 1,350,000 January 15, 2016 90 CD N/A April 13, 2016 100% Completed
13 Improvement of Covered Court & Brgy. Hall (Phase 2) Brgy. Uling City of Naga BT Construction 1,250,000 November 23, 2015 90 CD 30 CD March 24,2016 100% Completed 3/22/16
14 Rehabilitaion of Drainage Rizal St. Brgy. Central Pob. City of Naga A.T. Macrohon Construction Co. 2,374,607.68 November 23, 2016 90 CD 40 CD February 20, 2016 95% On-going
15 Construction of Lying-In and RHU Building Phase 5 Brgy. East Pob. City of Naga First Grandeur Builder 2,000,000 February 12, 2016 75 CD N/A April 26, 2016 100% Completed 4/20/16
16 Rehabilitation of Drainage Brgy. West Pob. City Of Naga Hoppers' Builders 977,008.153 March 11, 2016 45 CD N/A April 24, 2016 100% Completed 4/21/16
17 Construction of Reinforced  Box Culvert Brgy. North Pob. City of Naga A.T. Macrohon Construction Co. 4,100,000 March 11, 2016 85 CD N/A June, 2016 59.68% On Going
18 Fabrication and Installation of Street Lighting (Phase 2) Brgy. Bairan, City of Naga Hoppers' Builders 1,350,000 March 11, 2016 104 WD N/A August 4,2016 100% Completed 6/16/16
19 Construction of Covered Court Brgy. Cantao-an, City of Naga First Granduer Builders 3,000,000 March 21, 2016 125 CD N/A July 23, 2016 70% On-going
20 Installation of Doors and Windows and Painting of RHU & Lying-In (Phase 4) Brgy. East Pob. City of Naga First Grandeur Builders 3,546,423.02 March 21, 2016 75 CD N/A June 3, 2016 98% On-going
21 Construction of Multi-Purpose Bldg. Brgy. Uling, City of Naga First Granduer Builders 1,250,000 March 21, 2016 120 CD N/A July 18, 2016 80% On-going
22 Construction of 1 Storey Building RHU Expansion Brgy. East Pob. City of Naga First Granduer Builders 3,950,000 March 21, 2016 136 CD N/A August 3, 2016 60% On-going
23 Road Asphalting Upper Inoburan, City of Naga Quirante Construction 900,000 March 21, 2016 30CD N/A April 19, 2016 100% Completed 4/21/16
24 Construction of Perimeter Fence of Day Center Ground Brgy. Patag, City of Naga BT Construction & General Services 1,250,000 March 21, 2016 90 CD N/A June 18, 2016 100% Completed 6/17/16
25 Construction of Covered Court Brgy. Mayana, City of Naga BT Construction & General Services 2,000,000 March 21, 2016 120 CD N/A July 18, 2016 80% On-going
26 Road Concreting Brgy. Jaguimit, Sitio Bungtod, City of Naga WJC Construction Services 1,000,000 March 21, 2016 90 CD N/A June 18, 2016 100% Completed 6/17/16
27 Construction of Multi-purpose Bldg. Brgy. Lutac, City od Naga Cebu A.T. Macrohon Construction Co. 1,250,000 March 21, 2016 90 CD N/A June 18, 2016 90% On-going
28 Construction of Drainage Brgy. South Pob. City of Naga A.T. Macrohon Construction Co. 1,200,000 March 21, 2016 90 CD N/A June 18, 2016 100% Completed
29 Road Concreting Brgy. Langtad, Sitio Campaog, City of Naga A.T. Macrohon Construction Co. 1,250,000 March 21, 2016 90 CD N/A June 18, 2016 100% Completed 6/20/16
30 Construction of Footbridge and Road Concreting Brgy. Central Pob., City of Naga A.T. Macrohon Construction Co. 1,000,000 March 21, 2016 90 CD N/A June 18, 2016 60% On-going
31 Concreting of Basketball Court (3 Sitios) Brgy. Tagjaguimit A.T. Macrohon Construction Co. 1,250,000 March 21, 2016 120 CD N/A July 18, 2016 90% On-going
32 Construction of Slope Protection and Drainage Brgy. Alpaco, Sitio Kavisig, City of Naga A.T. Macrohon Construction Co. 1,250,000 March 21, 2016 90 CD N/A June 18, 2016 100% Completed
33 Road Concreting Brgy. Colon, City of Naga JV Bontilao Construction & Ent. 1,250,00 March 21, 2016 90 CD N/A June 18, 2016 30% Suspend(Still waiting for the Deed of Donation)
34 Street Lighting Brgy. South Pob. City of Naga Cebu Ferac Builders & Development

3,546,604.92

 

March 21,2016                                         

90 WD N/A July 22, 2016 100% Completed 6/30/16
35 Construction of Covered Court Completion Brgy Naalad, City of Naga Hoppers' Builder 2,785,000 March 21, 2016 120 CD N/A July 18, 2016 100% Completed 7/7/16
36 Construction of Multi-purpose Bldg. Brgy. Tangke, City of Naga A.T. Macrohon Construction Co. 1,250,000 March 21, 2016 120CD N/A July 18, 2016 5% On-going
37 Brgy. Road Concreting from Brgy. Hall to Sitio Og-og Brgy. Mainit, City of Naga A.T. Macrohon Construction Co. 1,000,000 March 21, 2016 90 CD N/A June 18, 20106 100% Completed 5/7/16
38 Construction of Covered Court (Phase 2) Brgy. Balirong, Sitio Pandayan, City of Naga A.T. Macrohon Construction Co. 1,350,000 March 11, 2016 78 CD N/A May 27, 2016 100% Completed
39 Construction of Reinforced Drainage Sito Sambag, Brgy. Tuyan, City of Naga Hoppers' Builders 1,250,000 March 21, 2016 120CD N/A July 18, 2016 100% Completed 5/27/16
40 Construction of Wall Partitioning @ 2nd Flr. of CTU (formely old Naga Public Market) Brgy. Central Pob., City of Naga JO Builders 2,600,000 March 21, 2016 120 CD N/A July 18, 2016 78% On Going
41 Construction of Reinforced Pathways and Drainage Brgy. Inayagan, City of Naga DT & C Construction 1,250,000 March 21, 2016 90CD N/A June 18, 2016 100% Completed
42 Road Concreting Brgy. Lanas, Sitio Baclay, City of Naga DT & C Construction 1,250,000 March 21, 2016 90CD N/A June 18, 2016 100% Completed
43 Construction of Open Canal w/ Slope Protection Brgy. Bairan, City of Naga First Granduer Builder 180,000 February 1, 2016 45CD N/A March 16, 2016 100% Completed
44 Demolition of Concrete Table, Partition & Sanitary lines of 2nd flr. & ground flr. of old public market Brgy. Central Pob., City of Naga Pakyaw 399,000 February 29,2016 75 CD N/A May 13, 2016 100% Completed 5/6/816
45 Road Concreting Brgy. West Pob., City of Naga Hoppers' Builders 174,587.303 February 29, 2016 25 CD N/A March 24, 2016 100% Completed 3/23/2016
46 Dismantling & Installation for REplacement Corroded Durarib Roofing @ Badminton Brgy. East Pob., City of Naga Pakyaw 530,000 March 14, 2016 40CD N/A April 22, 2016 100% Completed
47 Construction of Drainage Brgy. Lutac, City of Naga First Granduer Builders 100,000 February 1, 2016 30CD N/A March 1, 2016 100% Completed 3/1/16

 

 